Friday, February 24th

Jim started the exterior trim. It's been slow going as Hardi board is very hard to work with. It looks great though! Jim needs to get the electric service moved to complete the trim around the southwest corner.
Ed Lagnese gave me the best price for blueboard and plaster and I told him that I was going to give him the job. I am going to schedule him for the week of March 13th as the fireplace is due that week.
Sent out requests for quotes for wood doors and only got one bid back so far. Homestead Hardwoods quoted maple and poplar for us.